I have mapped out a schedule for a project in a bar chart.
I'm running into a problem where all my tasks are starting on the same date. The data points all start at the beginning of my year range. ex. June 1st.
I want the bar to reflect the correct start and end date and I'm not sure where my error is.
If I'm understanding what you're describing, you essentially need a 'blank' column to build a waterfall so the bars stagger. You then make that "blank" column 'no fill' so it doesn't show and the colored bars will only stretch between the dates you want them (not from the beginning)
If I'm understanding what you're describing, you essentially need a 'blank' column to build a waterfall so the bars stagger. You then make that "blank" column 'no fill' so it doesn't show and the colored bars will only stretch between the dates you want them (not from the beginning)
So you almost need like a 'blank/dummy' column to 'fill in' June 1-14 (in your example), and then the next column will start on June 15. You can right click individual columns to change their fill/formatting and there make it 'no fill' so you don't see it, making the June 15th column floating, essentially.